The Baglihar Setback
Pakistan OBSERVER, Thu, January,13, 2005.
Pervaiz Iqbal Cheema
The inability of both India and Pakistan to resolve the Baglihar Dam despite
the fact many news reports indicated that the differences have been narrowed
down certainly is a setback to the ongoing peace process. There is no doubt
that each failure tends to not only dampen hopes that may have been
exaggeratedly raised but also takes a toll of the incumbent enthusiasm and
goodwill. To reach some understanding both sides agreed to extend talks for
another day with the hope that they may be able to work out their differences
but failed to do so.
The construction on the
Baglihar dam project on the river Chenab started in 1999 though it was
conceived and approved much earlier. In order to quickly complete the project
the Indians have currently employed several hundreds of engineers and the
labourers. The recent reports indicate that they have hired the services of
many more individuals to speed up the construction work with ostensible aim of
confronting Pakistan with a fait accompli.
The Pakistanis had
conveyed their objections and reservation regarding the design of the project
despite the fact that the requested requisite data was never supplied quickly.
According to the Indus water treaty of 1960, the unrestricted flow of Chenab
waters was allocated to Pakistan. However it needs to be mentioned here that
India was allowed the use of limited waters of western rivers for development
of irrigation, generation of electric power along with other uses that were
spelled out in the annexes of the treaty.
Pakistan’s objection
and reservations about the project primarily deals with the design which
allows more flow of waters than what is permissible under the Indus water
treaty. On learning about the construction the Pakistanis raised their
objections which India, tried to ignore initially but later began to respond
somewhat hesitantly. Even the Pakistanis were allowed to visit the site. After
the visit the Pakistanis became even more convinced that if the dam is
constructed in accordance with the current design, Pakistan is likely to lose
7000 to 8000 cusecs a day. This implies that Pakistan will have to learn to
live with these losses.
Cognizant of the likely
losses the Pakistanis initially tried to have the necessary rectification of
design done at the Indus Commissioners level but once they were unable to
secure a desired agreement, the dispute-level was raised to the level of
secretaries of water and power. The two sides have met but have so far not
been able to work out a mutually acceptable agreement. In the recent meeting
of the secretaries the Pakistanis have listed six objections relating to
pondage level, spillways, level of intake tunnels, regulatory weir level,
height of gates and elevation of tunnels etc.
To address Pakistani
reservations and objections the recent talks which were originally scheduled
for two days, were extended for another day. In many ways it was a last ditch
effort on the part of the Pakistanis to secure the desired rectification.
While the Indians are generating the impression that they are considering all
the Pakistani objections and reservations rather seriously and they wanted
Pakistanis to continue bilateral talks, the Pakistani stance, as reported in
the section of Pakistani press, was that the ‘talks could be continued only if
India stopped work on the dam’. India did not agree to this condition and have
opted for continuation of construction which is not acceptable to the
Pakistanis.
The question that needs
to be addressed here is that why did the Indian refuse to stop the
construction work in order to have another round of bilateral talks and opted
to carry on with their hard approach? Many reasons account for such pursuits.
First, it appears that Indian believe that construction should not only
continue but work should be speeded up with a view to present the Pakistanis
with a fait accompli. Since the over prevailing atmosphere has considerably
improved, the Pakistanis could be brought around to accept the Indian
interpretation once the construction is complete. Incentive or concessions in
some other areas might be employed at the time of presenting the
fait-accompli.
The second
interpretation is that India apparently believes that it can get away with its
own interpretation and the international community is unlikely to put
sufficient pressures forcing her to change. The lure of large market can
influence the policy pursuits of many nations. If Israel can get away and
continue to pursue its policy of construction of wall despite the verdict of
world court, India could do the same especially when one realises that wall
issue is far more important than the modification of dam’s design. Given the
world after 9/11 it would not be all that surprising if India ignores the
international pressures and effectively bypasses its commitments.
The third
interpretation that comes to ones mind is viewing it as a minor disrespect to
the obligations of the Indus Water treaty. If India can brush aside openly the
UN resolutions on the ongoing Kashmir dispute, the design issue could be
viewed as minor by many Indian officials. A close scrutiny of the Indian
policy pursuits especially its Kashmir policy clearly points towards such a
probability.
Given the above
mentioned situation what can and what should Pakistan do. Perhaps the only way
out for Pakistan is to take the case to the World Bank in accordance with the
provisions of the treaty and seek the appointment of a neutral expert. India
has always opposed the involvement of a third party in any of its dispute. It
prefers to handle them on bilateral basis. Undoubtedly the bilateral tackling
of the mutual dispute is perhaps one the best way to resolve issues but what
happens if the two parties reach a dead-end. In such a situation it would be
appropriate to involve the third party.
After the failure of
current round of talks the Pakistani delegation came back to Pakistan. Now the
next appropriate stage is to approach the World Bank and secure the
appointment of a neutral expert. The decision to move to the next stage in its
efforts to resolve the dispute in accordance with the provisions of Indus
Waters treaty has been announced by the Pakistani Prime Minister who has
directed the concerned quarters to make necessary preparation on priority
basis for seeking World Bank arbitration. It is pertinent to mention here
that Pakistanis, in the past, had already stated that they would move the case
to the World Bank if the bilateral negotiation failed.
Judged by any yardstick
the failure to reach an agreement over the Baglihar dam is bound to take not
only a heavy chunk of existing goodwill and cordiality of atmosphere but would
also strengthen the belief that India is employing age old delaying tactics.
Whether or not this failure would adversely impact upon the ongoing composite
dialogue remains to be seen but there is no doubt it would certainly dampen
the existing optimism.
The author works for Islamabad Policy research Institute.
|